I think with the latest SE+K2 update the consumption rate of steam was adjusted and causes a bit of a problem. Standard steam turbines burn steam (of any temp higher than 415) at 83.3/s to generate 10MW of power. When the turbine is changed with your mod to 'high priority' the consumption rate caps out at 50/s which then only lets the generator create 6MW of power unless steam higher than 415 degrees is being supplied. So, only if i supply 480 degree steam or higher i can get the 10mw power out of the turbine.
Can we have the increased priority version of the generator keep the original(non-increased priority) steam consumption rate?